Resources/Documents/Deliverables

Publications

Published papers could be found at Zenodo A-WEAR community.

List of Deliverables [Public and Approved]

  • D1.1 Project and Financial Management Plan deliverable [Confidential] Approved on 03 Jan 2020
  • D1.2 Data Management and quality assurance plan [Public] Approved on 03 Jan 2020
  • D1.3 Collection of ethical clearance procedure and forms available at each participant [Public] Approved on 03 Jan 2020
  • D1.4 Project website [Public] Approved on 14 May 2019
  • D1.5 Progress Report/1st Periodic project report [Public] Approved on 03 Jan 2020
  • D1.6 Report on recruitment process and updated secondment plan [Public] Approved on 03 Jan 2020
  • D1.7 2nd Periodic project report [Public] Pending
  • D1.8 3rd Periodic project report [Public] Pending]
  • D1.9 4th periodic progress report [Public] Pending
  • D1.10 5th Periodic project report [Public] Pending
  • D1.11 Final project report [Public] Pending
  • D1.12 Meeting minutes of all AB and MB meetings [Confidential] Pending
  • D1.13 Supervisory Board of the network [Confidential] Approved on 14 May 2019
  • D1.14 Consortium Agreement [Confidential] Approved on 14 May 2019
  • D1.15 Signed administrative agreement to establish a joint/double/multiple Doctorate [Confidential] Approved on 03 Jan 2020
  • D2.1 State-of-the art and algorithms beyond SOTA for edge and fog computing in wearables [Public] Pending
  • D2.2 Novel D2D and edge computing architectures [Public] Pending
  • D3.1 Requirements definition and innovative storage and processing methods for social applications of wearables [Public] Pending
  • D3.2 Open-source SW and platforms for social applications in wearables [Public] Pending
  • D4.1 State-of-the-art and solutions beyond SOTA in wearables localization, privacy and trust [Public] Pending
  • D4.2 Proof-of-concept and experimental results for seamless and infrastructure-less localization of wearables [Public] Pending
  • D5.1 Wearable metrics and description WP5 interim research results [Public] Pending
  • D5.2 Innovative low-latency technologies for wearables [Public] Pending
  • D6.1 Plan for outreach, dissemination and exploitation [Public] Approved on 03 Jan 2020
  • D6.2 Webropol survey analysis based on stakeholders [Public] Pending
  • D6.3 Update on outreach, dissemination and exploitation in final year and beyond [Public] Pending
  • D7.1 Plan for training activities [Public] Approved on 03 Jan 2020
  • D7.2 PCDPs established and approved for each ESR [Public] Approved on 03 Jan 2020
  • D7.3 First report of training activities [Public] Pending
  • D7.4 Second report of training activities [Public] Pending
  • D7.5 Updated PCDPs for each ESR [Public] Pending
  • D7.6 Proceedings of all seasonal schools and workshops from Table 1.2b and final report of training activities [Public] Pending
  • D8.1 POPD – Requirement No. 1 [Confidential] Approved on 03 Jan 2020
  • D8.2 DU – Requirement No. 2 [Confidential] Approved on 03 Jan 2020
  • D8.3 H – Requirement No. 3 [Confidential] Approved on 03 Jan 2020

Milestones

  • M1 Start the recruitment of the fellows [Completed] 28 Feb 2019
  • M2 Project website up and running [Completed] 28 Feb 2019
  • M3 Complete Project Management Plan [Completed] 30 Jun 2019
  • M4 Double/joint PhD agreements between Beneficiaries completed [Completed] 30 Jun 2019
  • M22 Preparation of Training Plan [Completed] 30 Jun 2019
  • M5 Completion of ESR Recruitment [Completed] 31 Dec 2019
  • M19 LinkedIn, Twitter and Facebook groups for A-WEAR created [Completed] 31 Dec 2019
  • M20 Press release on A-WEAR after recruitment [Completed] 31 Dec 2019
  • M25 All recruited fellows enrolled in PhD programme [Completed] 31 Dec 2019
  • M6 State-of-the art review completed by all fellows [Completed] 31 Jan 2020
  • M26 Project Check [Completed] 31 Mar 2020
  • M11 List of crowdsensed parameters from wearables defined [Completed] 30 Jun 2020
  • M14 Comparative performance of sub-m positioning technologies in wearables [Completed] 30 Jun 2020
  • M7 Transfer of ESRs from literature review to main research phase 31 Dec 2020
  • M10 Proposed wearables network architecture published at the webpage 30 Apr 2021
  • M12 Open-source crowsensed collected data from wearables made available to the research community 31 May 2021
  • M8 First open-source SW from A-WEAR available (GitHub/Zenodo) 30 Jun 2021
  • M13 eHealth platform requirement definition 30 Jun 2021
  • M15 Privacy-aware solutions in wearables summarized at the webpage 30 Jun 2021
  • M16 Privacy-aware localization algorithms demonstrated 30 Jun 2021
  • M21 All fellows’ scientific profiles available on ResearchGate 30 Jun 2021
  • M17 Design recommendations for work safety through wearables available in public domain 31 Jul 2021
  • M18 Benchmarks and formally proven secure algorithms on IoWT provided 30 Sep 2021
  • M9 Journal papers submitted 31 Dec 2021
  • M23 First half of A-WEAR Workshops and Seasonal Schools completed 31 Dec 2021
  • M24 All fellows registered as PhD students at TUT and BUT (where credits are needed for PhD) collected at least 30 ECTS for their PhD studies 31 Dec 2021